Targeted Activities
Activity | Expected date for achievement |
---|---|
Feeder Metering | 30 June 2016 |
DT Metering | 30 June 2017 |
Consumer indexing & GIS Mapping | 30 Sept 2018 |
Upgradation of DT, Meters etc | 31 Dec 2017 |
Smart meter for consumers | > 500 Unit by Dec 17; >200 unit by Dec 2019 |
AT&C losses | 15% by FY 2019 |
Elimination ACS-ARR gap | FY 2019 |