Targeted Activities


Activity Expected date for achievement
Feeder Metering 30 June 2016
DT Metering 30 June 2017
Consumer indexing & GIS Mapping 30 Sept 2018
Upgradation of DT, Meters etc 31 Dec 2017
Smart meter for consumers > 500 Unit by Dec 17; >200 unit by Dec 2019
AT&C losses 15% by FY 2019
Elimination ACS-ARR gap FY 2019